Value Stream Mapping (VSM) Implementation as an Effort to Reduce Delays in the Procurement Process at PT DI
DOI:
https://doi.org/10.22441/ijiem.v2i3.11875Keywords:
Value stream mapping, Procurement, Waste, LeanAbstract
PT DI is an oil and gas company, to support its production a good procurement process is needed. Procurement is an activity to get goods and services in a transparent, effective, and efficient. Based on data in 2017, there is 148 procurement with a value of less than 2.5 billion carried out by PT DI, from that data there are 43% of the procurement completed exceeding the predetermined initial target. Based on data in 2017, the procurement of A4100000121 has the highest delay rate of 32 days, therefore it is necessary to identify waste as an effort to reduce the time delay. The method used is Value Stream Mapping, this method is used to identify processes that contain waste so that existing waste can be removed. Based on the results of the study there was a decrease in time between Current State VSM and Future State VSM with a total time at Current State VSM of 39425 minutes and Future State VSM of 23085 minutes so that the time was decreased by 16340 minutesDownloads
References
Adrianto, W. (2015). Analisis Penerapan Lean Production Process Untuk Mengurangi Lead Time Process Perawatan Engine (Studi Kasus PT. GMF Aeroasia) (Doctoral dissertation, Universitas Mercu Buana).
Abdulmalek, F. A., & Rajgopal, J. (2007). Analyzing the benefits of lean manufacturing and value stream mapping via simulation: A process sector case study. International Journal of Production Economics, 107(1), 223–236. https://doi.org/10.1016/j.ijpe.2006.09.009
Bampton, R., & Cowton, C. J. (2002). The e-interview. Forum Qualitative Sozialforschung, 3(2). https://doi.org/10.17169/fqs-3.2.848
Bar-Ilan, J. (2001). Data collection methods on the web for informetric purposes - A review and analysis. Scientometrics, 50(1), 7–32. https://doi.org/10.1023/A:1005682102768
Grewal, C. (2008). An initiative to implement lean manufacturing using value stream mapping in a small company. International Journal of Manufacturing Technology and Management, 15(3–4), 404–417. https://doi.org/10.1504/IJMTM.2008.020176
Haefner, B., Kraemer, A., Stauss, T., & Lanza, G. (2014). Quality value stream mapping. Procedia CIRP, 17, 254–259. https://doi.org/10.1016/j.procir.2014.01.093
Joosten, T., Bongers, I., & Janssen, R. (2009). Application of lean thinking to health care: Issues and observations. International Journal for Quality in Health Care, 21(5), 341–347. https://doi.org/10.1093/intqhc/mzp036
Khanghahi, M. E., & Azar, F. E. F. (2018). Direct observation of procedural skills (DOPS) evaluation method: Systematic review of evidence. Medical Journal of the Islamic Republic of Iran, 32(1), 254–261. https://doi.org/10.14196/MJIRI.32.45
Lacerda, A. P., Xambre, A. R., & Alvelos, H. M. (2016). Applying Value Stream Mapping to eliminate waste: A case study of an original equipment manufacturer for the automotive industry. International Journal of Production Research, 54(6), 1708–1720. https://doi.org/10.1080/00207543.2015.1055349
Natakusuma, M., Hidayatullah, N., & Purba, H. H. (2018). Reducing Turn around Time in Laboratory using Value Stream Mapping. International Journal of Recent Engineering Science, 5(1), 16–21. https://doi.org/10.14445/23497157/ijres-v5i1p104
Purba, H.H., Mukhlisin, M., Aisyah, S. (2018). Productivity improvement picking order by appropriate method, value stream mapping analysis, and storage design: a case study in automotive part center. Management and Production Engineering Review, 9(1), 71-81. DOI: 10.24425/119402
Setiawan, I., Tumanggor, O.S.P., Purba, H.H. (2021). Value Stream Mapping: Literature Review and Implications for Service Industry. Jurnal Sistem Teknik Industri, 23(2), 155-166. https://doi.org/10.32734/jsti.v23i2.6038
Snyder, H. (2019). Literature review as a research methodology: An overview and guidelines. Journal of Business Research, 104(March), 333–339. https://doi.org/10.1016/j.jbusres.2019.07.039
Trimarjoko, A., Mukhlis, D., Fathurohman, H., & Suwandi, S. (2020). Metode Value Stream Mapping dan Six Sigma untuk Perbaikan Kualitas Layanan Industri di Automotive Services Indonesia. Indonesian Journal of Industrial Engineering & Management, 1(2), 91-104. http://dx.doi.org/10.22441/ijiem.v1i2.8873
Tyagi, S., Choudhary, A., Cai, X., & Yang, K. (2014). Author ’ s Accepted Manuscript Value stream mapping to reduce the lead-time of product development process. Intern. Journal of Production Economics. https://doi.org/10.1016/j.ijpe.2014.11.002
Utomo, A. P. (2020). A Systematic Literature Review of Six Sigma Implementation in Services Industries. IJIEM (Indonesian Journal of Industrial Engineering & Management), 1(1), 45–57. http://dx.doi.org/10.22441/ijiem.v1i1.8846
Yansen, O., & Bendatu, L. Y. (2013). Perancangan Value Stream Mapping dan Upaya Penurunan Lead time pada Bagian Procurement-Purchasing di PT X. Titra, 1(2), 9–16.