ANALISA OPTIMALISASI PEMBORAN SUMUR EKSPLORASI ABC-1 PT. XYZ DENGAN METODE CPM DAN PERT
DOI:
https://doi.org/10.22441/indikator.v4i2.9999Kata Kunci:
Upstream Oil and Gas Projects, CPM, PERT, Crashing, Cost SlopeAbstrak
Abstract.
Looking at the current conditions where Indonesia's oil and gas production is declining day by day, Indonesia must become a net oil importer country to meet domestic needs. One of the investors for domestic upstream oil and gas activities is PT. XYZ. The company has conducted upstream oil and gas activities in the form of ABC-1 exploration well drilling. In the ABC-1 exploration well drilling process faces a security risk that develops into a time and cost risk. In ABC-1 exploration well data processing using CPM and PERT methods. The data that is processed are program data, realization data and ideal data. The results of this study found the ideal time to complete the project with the CPM method is 708 days while the PERT method is 698 days with a standard deviation (z) of 7.07 days so that the completion time becomes 691 days. With an ideal time to accelerate one project completion for 543 days with an additional cost of $ 52,231 and a total cost of $ 11,017,161. For a cost slope of $ 317. If two accelerated completion of the project is used for 498 days with an additional cost of $ 80,371 and a total cost of $ 11,045,301. For a cost slope of $ 383.
Abstrak.
Memandang pada kondisi saat ini dimana produksi minyak dan gas bumi Indonesia yang kian hari menurun menyebabkan Indonesia harus menjadi net oil importer country untuk memenuhi kebutuhan dalam negeri. Salah satu investor untuk kegiatan hulu migas dari dalam negeri adalah PT. XYZ. Perusahaan ini sudah melakukan kegiatan hulu migas berupa pemboran sumur eksplorasi ABC-1. Pada proses pemboran sumur eksplorasi ABC-1 menghadapi resiko keamanan yang berkembang menjadi resiko waktu dan biaya. Pada pengolahan data sumur ekplorasi ABC-1 dengan menggunakan metode CPM dan PERT. Data yang diolah yaitu data program, data realisasi dan data ideal. Hasil penelitian ini didapatkan waktu ideal penyelesaian proyek dengan metode CPM adalah 708 hari sedangkan dengan metode PERT adalah 698 hari dengan standard deviasi (z) yaitu 7,07 hari sehingga waktu penyelesai menjadi 691 hari. Dengan waktu ideal percepatan satu penyelesaian proyek selama 543 hari dengan biaya tambahan sebesar $52.231 dan total biaya sebesar $11.017.161. Untuk cost slope sebesar $317. Jika digunakan percepatan dua penyelesaian proyek selama 498 hari dengan biaya tambahan sebesar $80.371 dan total biaya sebesar $11.045.301. Untuk cost slope sebesar $383.
Unduhan
Diterbitkan
Cara Mengutip
Terbitan
Bagian
Lisensi
The copyright to this article is transferred to Universitas Mercu Buana (UMB) if and when the article is accepted for publication. The undersigned hereby transfers any and all rights in and to the paper including without limitation all copyrights to UMB. The undersigned hereby represents and warrants that the paper is original and that he/she is the author of the paper, except for material that is clearly identified as to its original source, with permission notices from the copyright owners where required. The undersigned represents that he/she has the power and authority to make and execute this assignment.
We declare that:
1. This paper has not been published in the same form elsewhere.
2. It will not be submitted anywhere else for publication prior to acceptance/rejection by this Journal.
3. A copyright permission is obtained for materials published elsewhere and which require this permission for reproduction.
Furthermore, I/We hereby transfer the unlimited rights of publication of the above mentioned paper in whole to UMB. The copyright transfer covers the exclusive right to reproduce and distribute the article, including reprints, translations, photographic reproductions, microform, electronic form (offline, online) or any other reproductions of similar nature.
The corresponding author signs for and accepts responsibility for releasing this material on behalf of any and all co-authors. This agreement is to be signed by at least one of the authors who have obtained the assent of the co-author(s) where applicable. After submission of this agreement signed by the corresponding author, changes of authorship or in the order of the authors listed will not be accepted.
Retained Rights/Terms and Conditions
1. Authors retain all proprietary rights in any process, procedure, or article of manufacture described in the Work.
2. Authors may reproduce or authorize others to reproduce the Work or derivative works for the authors personal use or for company use, provided that the source and the UMB copyright notice are indicated, the copies are not used in any way that implies UMB endorsement of a product or service of any employer, and the copies themselves are not offered for sale.
3. Although authors are permitted to re-use all or portions of the Work in other works, this does not include granting third-party requests for reprinting, republishing, or other types of re-use.
This work is also licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.