Analisis Penggunaan Bekisting Konvensional, Baja dan Sistim Peri dari Segi Biaya pada Struktur Pier Konstruksi Ramp On/Off Jalan Tol

Hamonangan Girsang

Abstract


 

Formwork is a concrete mold reference or temporary structural element in the work of construction that also contributes to the cost of project implementation, several types of formworks are using in the construction works are conventional, steel, aluminum, peri-system, fiberglass, that’s will make their contribution in the implementation of concrete construction structures. the selection for use of the formwork method are important role in achieving the success of the structural work, especially in the terms of costing because it is necessary to do a thorough analysis related to the formwork material used and the method of implementation. This study aims to compare the costs of using polymer system peri formwork, conventional formwork, and steel plate formwork in pier structure construction work.

This research was conducted using descriptive analysis method, the data obtained from various sources were then analyzed and used for the research process in comparing costs. The construction structure reviewed in this study is specifically the pier structure construction consisting of pilecap, column and pierhead.

After analyzing the use of bakesting by reviewing of cost performance, the use of polymer system peri formwork materials required costs IDR 773,879,700,- and with conventional formwork materials required costs IDR 1,391,152,241,- and using steel formwork requires IDR 1,091,953,197,- thus the comparative price index the three formwork materials are 1: 1.8: 1.4.


Full Text:

PDF

References


Deviana Cahyani, Anjas Handayani, (2021), Analysis Comparison of Plate and Beam Formwork Using Semi Conventional Formwork with Aluminium Formwork System in Terms of Cost and Duration on Vasanta Innopark Project, Journal of Words Comference, 3 (1), 32-39

F. W. Helyar, McGraw Hill, (1978), Construction Estimating and Costing. Toronto, Canada.

Hario Surya Pratama, Rosaria Kristy Anggraeni, Arif Hidayat, Riqi Radian Khasani (2017) Analisa perbandingan penggunaan bekisting konvensional, semi sistem, dan sistem (peri) pada kolom gedung bertingkat, Jurnal Karya Teknik Sipil, 6(1), 303-313

Ihsan, R.I. (2020) Analisis

Perbandingan Waktu Dan Biaya

Bekisting Metode Konvensional Dengan Metode Aluminium Formwork Pada Proyek Bess Mansion Surabaya.

I Made Pandu Weda Wiguna, I Gusti Agung Adnyana Putera, G.A.P Candra Dharmayanti (2018) Analisis Penghematan Biaya Penggunaan Bekisting Pelat Lantai Konvensional Model Panel Pada Bangunan Tipikal (Studi Kasus Pada Proyek Amartha Residence), Jurnal Spektran, 6(1), (59-64).

Ms. Aakanksha Dilip Chaudhary, (2017) Study of Tunnel Formwork System & Comparative Analysis with Conventional Formwork

https://www.ijser.org/online International Journal of Scientific & Engineering Research Volume 8 (5).

M Rizal Wahyudi, Astuti Boer (2019), Tingkat Efisiensi Biaya Pekerjaan Bekisting Struktur Core Wall Menggunakan Metode Semi Sistem dan Climbing System, Jurnal Saintis, 19(2), (51-59)

Muhamad, A. (2005). Model Penilaian Kewajaran Harga Penawaran Kontraktor dengan Sistem Evaluasi Nilai. Jurnal Teknik Sipil, 12(3), 185–200.

Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat Nomor 1 tahun 2022, tentang pedomana penyusunan perkiraan biaya pekerjaan konstruksi bidang pekerjaan umum dan perumahan rakyat.

Steven, Jane Sekarsari Tamtana (2020)., Penerapan Value Engineering dalam pemilihan jenis bekisting kolom beton pada konstruksi gedung bertingkat Jurnal Mitra Teknik Sipil, Volume 3(2), (267-268).

Susanti, I. I. (2019). Analisa Perbandingan Metode Konvensional, Desklab dan Bondek pada Pekerjaan Bekisting Jembatan Girder Tipe I Pada Proyek Jalan Tol Bogor–Ciawi–Sukabumi. Rekayasa Sipil, 8(2), (50-57).

SNI 7973: 2013, Spesifikasi Desain untuk Konstruksi Kayu.




DOI: http://dx.doi.org/10.22441/jrs.2023.v12.i1.05

Refbacks

  • There are currently no refbacks.


Copyright (c) 2023 Rekayasa Sipil

JURNAL REKAYASA SIPIL
Fakultas Teknik Universitas Mercu Buana
Jl. Raya Meruya Selatan, Kembangan, Jakarta 11650
Tlp./Fax: +62215871335
p-ISSN: 2252-7699
e-ISSN: 2598-5051
http://publikasi.mercubuana.ac.id/index.php/JRS

email: [email protected]

Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Web
Analytics Made Easy - StatCounter
View My Stats

.