ANALISIS JALUR KRITIS UNTUK MENGATASI KETERLAMBATAN PROSES PEMASANGAN PRODUK INTERIOR FURNITURE DENGAN METODE PERT PADA SALAH SATU PROYEK PT PAP CABANG BANDUNG
Abstract
Abstract. This thesis aims to analyze the critical path in the process of installation
of one project PT PAP branch Bandung. This study uses a network diagram
(PERT) to identify the critical path on each element of the work. The number of
products in the studied projects totaling 13 units of product. The initial step in this
research by calculating the standard time of the measurement of working time
every element of the process to 13 the number of products in the studied projects.
Critical path analysis using QM program for Windows. Analysis of the critical
path in the PERT method provides the possibility of project completion faster
compared to before analysis. Identify the cause of the problem of delays in the
completion of the entire project using the RCA (Root Cause Analysis). There are
two main problems based on the Pareto diagram are the problems and
shortcomings rework delivery. The main factor of rework problem is the
weakness of the monitoring system and communication supervisor and the limited
number of senior artisan. Improvement efforts undertaken in this research is to
increase communication and monitoring system with regular reports and conduct
skills training for junior builders.
Keywords: Project Management, Measurement of working time, PERT method,
RCA
Downloads
Downloads
How to Cite
Issue
Section
License
The copyright to this article is transferred to Universitas Mercu Buana (UMB) if and when the article is accepted for publication. The undersigned hereby transfers any and all rights in and to the paper including without limitation all copyrights to UMB. The undersigned hereby represents and warrants that the paper is original and that he/she is the author of the paper, except for material that is clearly identified as to its original source, with permission notices from the copyright owners where required. The undersigned represents that he/she has the power and authority to make and execute this assignment.
We declare that:
1. This paper has not been published in the same form elsewhere.
2. It will not be submitted anywhere else for publication prior to acceptance/rejection by this Journal.
3. A copyright permission is obtained for materials published elsewhere and which require this permission for reproduction.
Furthermore, I/We hereby transfer the unlimited rights of publication of the above mentioned paper in whole to UMB. The copyright transfer covers the exclusive right to reproduce and distribute the article, including reprints, translations, photographic reproductions, microform, electronic form (offline, online) or any other reproductions of similar nature.
The corresponding author signs for and accepts responsibility for releasing this material on behalf of any and all co-authors. This agreement is to be signed by at least one of the authors who have obtained the assent of the co-author(s) where applicable. After submission of this agreement signed by the corresponding author, changes of authorship or in the order of the authors listed will not be accepted.
Retained Rights/Terms and Conditions
1. Authors retain all proprietary rights in any process, procedure, or article of manufacture described in the Work.
2. Authors may reproduce or authorize others to reproduce the Work or derivative works for the authors personal use or for company use, provided that the source and the UMB copyright notice are indicated, the copies are not used in any way that implies UMB endorsement of a product or service of any employer, and the copies themselves are not offered for sale.
3. Although authors are permitted to re-use all or portions of the Work in other works, this does not include granting third-party requests for reprinting, republishing, or other types of re-use.