Analysis of project work using earned value management and precedence diagram method in manufacturing system projects
DOI:
https://doi.org/10.22441/oe.2024.v16.i2.114Kata Kunci:
earn value management, precedence diagram method, MS ProjectAbstrak
PT. Weiss Tech has received a project order for the fabrication and installation of coffee packaging production machines from PT.XYZ, scheduled to start on June 19, 2023, with a deadline of June 24, 2024, spanning 54 weeks. The project has been ongoing for 16 weeks with an update indicating that only 20% of the planned progress has been achieved, which suggests that it may not be completed on time. To evaluate the project's performance, the EVM method will be used to identify critical tasks and reduce the project duration using the Precedence Diagram Method with the help of MS Project software. The evaluation shows negative values for CV and SV variances, as well as performance index SPI<1 and CPI<1, indicating poor project performance. The critical tasks identified include electrical & instrument installation, machine & utility installation, trial work, assembly, quality control, polishing, milling, turning, cutting, and design. Design work has been identified as the most influential on the critical path. By rescheduling the project plan, positive values for CV and SV have been achieved. With the SPI value of 1.13 and CPI value of 1, it can be concluded that future project performance will be completed faster and within budget.
Unduhan
Referensi
Ahadis, M. I. H., Haryono, I., & Puspita, I. A. (2020). Pengukuran Kinerja Waktu Proyek Menggunakan
Metode Earned Value Management (EVM) Dan Mengoptimalkan Waktu Proyek Menggunakan Precedence Diagramming Method (PDM) Pada Proyek Renovasi Ruangan PT. XYZ. E-Proceeding of Engineering, 7(2), 5521–5528.
Caintan, M., & Suwarno. (2022). Computer Based Information System Journal Perancangan dan
Pengembangan Aplikasi Pendukung Proses Manufaktur dalam Penyusunan Palet Menggunakan Metodologi Prototyping. CBIS JOURNAL, 10(01). http://ejournal.upbatam.ac.id/index.php/cbishttp://ejournal.upbatam.ac.id/index.php/cbis
Dinata, G., Muttaqin, A., & Darsin, M. (2020). RANCANG BANGUN DAN UJI PERFORMASISTEM
KENDALI PEMBERIAN FLUIDA PERMESINAN MQL BERBASIS ARDUINO. REKAYASA MESIN, 11, 97–104.
Farrel Ghiffary, M., Abdul Mukti, F., Zulfa Geofani Firdaus, A., Nugroho Sulistyantoro, T., & Farrel
Ghiffary Muhammadfarrelghiffary, M. (2023). Analisis progres realisasi proyek terhadap biaya pada proyek jembatan kereta api rangka baja Surakarta. Proceeding Civil Engineering Research Forum, 3, 63–71.
Nabil, R., Furuhitho, X., Setiawan, L., Susanto, R., & Slameto, P. (2023). Perencanaan Pengendalian Biaya dan Waktu pada Proyek Pembangunan Rumah Susun Stie Tazkia Cendikia Bogor dengan Metode Earned Value. Journal Of Social Science Research, 3, 7591–7600.
Ginting, E. S., Charin, D., & Tarigan, N. (2023). Penjadwalan Produksi Celana Katun Menggunakan Metode Heuristic Pour. EE Conference Series, 178–181. https://doi.org/10.32734/ee.v6i1.1802
Luntungan, C., Arsjad, T. T., & Mangare, J. B. (2023). Analisis Penjadwalan Proyek Dengan Metode Precedence Diagram Method (PDM) Menggunakan Konsep Cadangan Waktu Pada Proyek Pembangunan Jembatan Sosongian Minahasa Selatan. Tekno, 21(85), 1690–1698.
Mantovani, M. R., & Beatrix, M. (n.d.). EVALUASI PENGENDALIAN BIAYA DENGAN METODE CRITICAL PATH METHOD (CPM) MENGGUNAKAN MICROSOFT PROJECT (STUDI KASUS: PEKERJAAN TAHAP VII PROYEK PERKUATAN STRUKTUR DERMAGA BERLIAN TANJUNG PERAK SURABAYA). Jurnal Ilmiah Teknik Dan Manajemen Industri, 3(1), 2023–2721. https://doi.org/10.46306/tgc.v3i1
Nalawade, S., Ghode, O., & Vaidya, P. (2019). Earn value analysis of construction project using primavera p6. CIKITUSI JOURNAL FOR MULTIDISCIPLINARY RESEARCH, 6(5), 514–522. http://cikitusi.com/
Proboretno, W., Witjaksana, B., & Tjendani, H. T. (2024). ANALYSIS OF COST AND TIME PERFORMANCE IN THE WADUNGASRI MARKET CHANNEL NORMALIZATION WORK IN SIDOARJO USING THE EARNED VALUE METHOD. INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, 3(2). https://ojs.transpublika.com/index.php/IJATEIS/
Project Management Institute, & Agile Alliance. (2017). A guide to the project management body of knowledge (PMBOK guide).
Reski Meliya, K., Purnama Sari, D., Arrie Rafshanjani, M., & Artikel, H. (2022). ETNIK : Jurnal Ekonomi-Teknik Evaluasi Pelaksanaan Pembangunan Proyek Dengan Menggunakan Metode Earnede Value Informasi Artikel. Ekonomi Teknik, 1, 374–382.
Supardi, S., Ahmadsyah, A., Urip Sumoharjo Km, J., Panakkukang, K., Makassar, K., & Selatan, S. (2021). Tinjauan Waktu Pelaksanaan Proyek Menggunakan Microsoft Project 2021 pada Pembangunan Pesantren Entrepeneurship Kabupaten Lebak Provinsi Banten. Teknik Sipil, 8, 159–169.
Veronika, J., & Ginting, B. (2020). Metode Earned Value Pada Pengendalian Proyek Pembangunan Gedung Sekolah SD Methodist-an Pancur Batu. Journal of Economics and Accounting, 1, 6–10.
Unduhan
Diterbitkan
Cara Mengutip
Terbitan
Bagian
Lisensi
The copyright to this article is transferred to Universitas Mercu Buana (UMB) if and when the article is accepted for publication. The undersigned hereby transfers any and all rights in and to the paper including without limitation all copyrights to UMB. The undersigned hereby represents and warrants that the paper is original and that he/she is the author of the paper, except for material that is clearly identified as to its original source, with permission notices from the copyright owners where required. The undersigned represents that he/she has the power and authority to make and execute this assignment.
We declare that:
1. This paper has not been published in the same form elsewhere.
2. It will not be submitted anywhere else for publication prior to acceptance/rejection by this Journal.
3. A copyright permission is obtained for materials published elsewhere and which require this permission for reproduction.
Furthermore, I/We hereby transfer the unlimited rights of publication of the above mentioned paper in whole to UMB. The copyright transfer covers the exclusive right to reproduce and distribute the article, including reprints, translations, photographic reproductions, microform, electronic form (offline, online) or any other reproductions of similar nature.
The corresponding author signs for and accepts responsibility for releasing this material on behalf of any and all co-authors. This agreement is to be signed by at least one of the authors who have obtained the assent of the co-author(s) where applicable. After submission of this agreement signed by the corresponding author, changes of authorship or in the order of the authors listed will not be accepted.
Retained Rights/Terms and Conditions
1. Authors retain all proprietary rights in any process, procedure, or article of manufacture described in the Work.
2. Authors may reproduce or authorize others to reproduce the Work or derivative works for the authors personal use or for company use, provided that the source and the UMB copyright notice are indicated, the copies are not used in any way that implies UMB endorsement of a product or service of any employer, and the copies themselves are not offered for sale.
3. Although authors are permitted to re-use all or portions of the Work in other works, this does not include granting third-party requests for reprinting, republishing, or other types of re-use.