Combination of value stream mapping (VSM) method and kanban system to reduce time waste in the production process of making parts for the four-wheel vehicle industry

Vebina Sheila Pasha, Jacky Chin, Hibarkah Kurnia

Abstract


Fulfilling orders from customers in the automotive industry is a necessity that inevitably causes problems that arise in product delivery to customers due to production delays and decreased production yields. The production process often experiences wasted time in the production process of four-wheeled vehicle spare parts. This research aims to reduce production process time, provide solutions to reduce waste and increase the number of four-wheeled vehicle spare parts produced. This research method uses the Lean Manufacturing (LM) approach by combining the Value Stream Mapping (VSM) method with Kanban system improvements, the application of Root Cause Analysis (RCA), and the Kaizen method. This research found that four factors cause waste in process time, including environmental factors, methods, humans, and machines. This research produces the right solution in the relay out of the Assembly and Final Inspection production processes, as well as the use of the e-kanban system in material and product inventory. The research results have reduced the production process time from 17.10 days to 10.05 days, meaning a decrease of 41.22%. This affected production results which increased from an average monthly production of 42,917 pcs to 60,157 pcs, meaning an increase of 128.65%.


Keywords


increase production; kaizen; re-layout; reduce process time; root cause analysis

Full Text:

PDF

References


Aisyah, S., Purba, H. H., Jaqin, C., Amelia, Z. R., & Adiyatna, H. (2021). Identification of implementation of Lean, Agile, Resilient, and Green (LARG) approach in Indonesia's automotive industry. Journal Europeen Des Systemes Automatises, 54(2), 317–324. https://doi.org/10.18280/JESA.540214

Aprianto, T., Nuryono, A., Setiawan, I., Kurnia, H., & Purba, H. H. (2022). Waste Analysis in the Speaker Box Assy Process to Reduce Lead Time in the Electronic Musical Instrument Industry. Quality Innovation Prosperity, 26(3), 53–65. https://doi.org/10.12776/qip.v26i3.1744

Ayu, F. T. B. (2018). Rekayasa Perbaikan Proses Produksi Boneka Dengan Integrasi Metode Line Balancing Dan Value Stream Mapping. Operations Excellence: Journal of Applied Industrial Engineering, 10(3), 294. https://doi.org/10.22441/oe.v10.3.2018.009

Castro, S., & Riedel, C. (2017). Assessment of the Implementation of Manufacturing Excellence in a Fiber-Based Packaging Manufacturing Environment. Procedia CIRP, 63, 113–118. https://doi.org/10.1016/j.procir.2017.03.104

Chiarini, A., Baccarani, C., & Mascherpa, V. (2018). Lean production, Toyota Production System and Kaizen philosophy: A conceptual analysis from the perspective of Zen Buddhism. TQM Journal, 30(4), 425–438. https://doi.org/10.1108/TQM-12-2017-0178

Fam, S. F., Ismail, N., Yanto, H., Prastyo, D. D., & Lau, B. P. (2018). Lean manufacturing and overall equipment efficiency (OEE) in paper manufacturing and paper products industry. Journal of Advanced Manufacturing Technology, 12(1 Special Issue 2), 461–474.

Haviana, E., & Hernadewita, H. (2019). Productivity improvement in the rubber production process using the value stream mapping method to eliminate waste. Operations Excellence: Journal of Applied Industrial Engineering, 11(2), 119. https://doi.org/10.22441/oe.v11.2.2019.023

Herdiansyah, D. (2020). Perancangan Dan Penerapan Sistem Kanban Di Pt Xy. Jurnal Ilmiah Teknologi Infomasi Terapan, 6(2), 57–64. https://doi.org/10.33197/jitter.vol6.iss2.2020.330

Hidayat, A. A., Kholil, M., Haekal, J., Ayuni, N. A., & Widodo, T. (2021). Lean Manufacturing Integration in Reducing the Number of Defects in the Finish Grinding Disk Brake with DMAIC and FMEA Methods in the Automotive Sub Industry Company. International Journal Of Scientific Advances, 2(5), 713–718. https://doi.org/10.51542/ijscia.v2i5.7

Ikatrinasari, Z. F., Hasibuan, S., & Kosasih, K. (2018). The Implementation of Lean and Green Manufacturing through Sustainable Value Stream Mapping. IOP Conference Series: Materials Science and Engineering, 453(1), 1–10. https://doi.org/10.1088/1757-899X/453/1/012004

Jaqin, C., Kurnia, H., Purba, H. H., Molle, T. D., & Aisyah, S. (2023). Lean Concept to Reduce Waste of Process Time in the Plastic Injection Industry in Indonesia. Nigerian Journal of Technological Development, 20(2), 73–82. https://doi.org/10.4314/njtd.v18i4.1396

Khan, R. M., & Mushtaq, A. (2022). Material Selection and Manufacturing of Halogen-Based Headlamps for Two-Wheeler Vehicle Technologies. Iranian Journal of Chemistry and Chemical Engineering, 41(1), 88–108. https://doi.org/10.30492/IJCCE.2021.121678.3976

Kurnia, H., Jaqin, C., Purba, H. H., & Setiawan, I. (2021). Implementation of Six Sigma in the DMAIC Approach for Quality Improvement in the Knitting Socks Industry. Tekstilvemuhendis, 28(124), 269–278. https://doi.org/10.7216/1300759920212812403

Kurnia, H., Setiawan, I., & Hernadewita. (2022). Integrasi Lean dan Green Manufacturing Untuk mengurangi Pemborosan Proses dan Limbah Kertas Rekrutmen Karyawan Pada Industri Manufaktur di Indonesia. Jurnal Rekayasa Sistem Industri, 11(2), 145–156. https://doi.org/https://doi.org/10.26593/jrsi.v11i2.5608

Kurniawan, W., Raharto, R., & Muryanto, M. (2022). Implementasi Kanban untuk Meminimalisir Kesalahan Penempatan pada Inventory System. Widya Cipta: Jurnal Sekretari Dan Manajemen, 6(2), 162–167. https://doi.org/10.31294/widyacipta.v6i2.13658

Lemadi, G. (2023). Implementation Of The Kanban System To Improve The Effectiveness Of Production Processes In The Food Industry. Jurnal Baut Dan Manufaktur, 5(1), 31–42.

Martins, B., Silva, C., Silva, D., MacHado, L., Brás, M., Oliveira, R., Carvalho, T., Silva, V., & Lima, R. M. (2021). Implementation of a Pull System Case Study of a Polymeric Production System for the Automotive Industry. Management Systems in Production Engineering, 29(4), 253–259. https://doi.org/10.2478/mspe-2021-0031

Masuti, P. M., & Dabade, U. A. (2019). Lean manufacturing implementation using value stream mapping at the excavator manufacturing company. Materials Today: Proceedings, 19(3), 606–614. https://doi.org/10.1016/j.matpr.2019.07.740

Mirzaei, N., Nejad, M. G., & Fernandes, N. O. (2021). Combining Line Balancing Methods and Discrete Event Simulation: A Case Study from a Metalworking Company. International Journal of Industrial Engineering and Management, 12(1), 14–24. https://doi.org/10.24867/IJIEM-2020-1-273

Nallusamy, S., & Adil Ahamed, M. A. (2017). Implementation of lean tools in an automotive industry for productivity enhancement - A case study. International Journal of Engineering Research in Africa, 29(1), 175–185. https://doi.org/10.4028/JERA.29.175

Pratiwi, A. I., & Santosa, R. Y. (2019). Improvement proses picking delivery pada perusahaan jasa warehouse dan logistik dengan pendekatan sistem kanban. 1st Conference on Industrial Engineering and Halal Industries (CIEHIS), 1(1), 169–176.

Purba, H. H., Mukhlisin, & Aisyah, S. (2018). Productivity improvement picking order by an appropriate method, value stream mapping analysis, and storage design: A case study in the automotive part center. Management and Production Engineering Review, 9(1), 71–81. https://doi.org/10.24425/119402

Rifqi, H., Zamma, A., Souda, S. B., & Hansali, M. (2021). Lean manufacturing implementation through DMAIC approach: A case study in the automotive industry. Quality Innovation Prosperity, 25(2), 54–77. https://doi.org/10.12776/qip.v25i2.1576

Romeira, B., Cunha, F., & Moura, A. (2021). Development and Application of an e-Kanban System in the Automotive Industry. International Conference on Industrial Engineering and Operations Management, 613–624. http://ieomsociety.org/proceedings/2021monterrey/101.pdf

Rose, A. N. M., Mohamed, N. M. Z. N., Ab Rashid, M. F. F., Noor, H. M., & Mohd, A. (2020). Improving productivity through value stream mapping (VSM): A case study at electrical & electronic company. Journal of Physics: Conference Series, 1532(1). https://doi.org/10.1088/1742-6596/1532/1/012005

Salvador, R., Piekarski, C. M., & Francisco, A. C. de. (2017). Approach of the Two-way Influence Between Lean and Green Manufacturing and its Connection to Related Organisational Areas. International Journal of Production Management and Engineering, 5(2), 73. https://doi.org/10.4995/ijpme.2017.7013

Santosa, W. A., & Sugarindra, M. (2018). Implementation of lean manufacturing to reduce waste in the production line with value stream mapping approach and Kaizen in division sanding upright piano, a case study in PT. X. MATEC Web of Conferences, 154, 8–11. https://doi.org/10.1051/matecconf/201815401095

Setiawan, B., Setiawan, I., Kurnia, H., Wahid, M., & Purba, H. H. (2022). Implementasi Metode Value Stream Mapping Pada Industri: Tinjauan Literatur Sistematis. Inaque : Journal of Industrial and Quality Engineering, 10(2), 103–116. https://doi.org/10.34010/iqe.v10i2.5989

Setiawan, S., Setiawan, I., Jaqin, C., Prabowo, H. A., & Purba, H. H. (2021). Integration of Waste Assessment Model and Lean Automation to Improve Process Cycle Efficiency in the Automotive Industry. Quality Innovation Prosperity, 25(3), 48–64. https://doi.org/10.12776/qip.v25i3.1613

Singh, J., Singh, H., Singh, A., & Singh, J. (2020). Managing industrial operations by lean thinking using value stream mapping and Six Sigma in manufacturing unit: Case studies. In Management Decision (Vol. 58, Issue 6). https://doi.org/10.1108/MD-04-2017-0332

Sjarifudin, D., & Kurnia, H. (2022). The PDCA Approach with Seven Quality Tools for Quality Improvement Men's Formal Jackets in Indonesia Garment Industry. Jurnal Sistem Teknik Industri (JSTI), 24(2), 159–176. https://doi.org/10.32734/jsti.v24i2.7711

Sjarifudin, D., Kurnia, H., Purba, H. H., & Jaqin, C. (2022). Implementation of the Six Sigma approach for increasing the quality of formal men’s jackets in the garment industry. Jurnal Sistem Dan Manajemen Industri, 6(1), 33–44. https://doi.org/10.30656/jsmi.v6i1.4359

Sumanto, S., & Marita, L. S. (2017). Penerapan Sistem Just In Time Persediaan Di Produksi Studi Kasus : PT. Nitto Materials Indonesia. J I M P - Jurnal Informatika Merdeka Pasuruan, 2(3), 1–11. https://doi.org/10.37438/jimp.v2i3.75

Tannady, H., Gunawan, E., Nurprihatin, F., & Wilujeng, F. R. (2019). Process improvement to reduce waste in the biggest instant noodle manufacturing company in Southeast Asia. Journal of Applied Engineering Science, 17(2), 203–212. https://doi.org/10.5937/jaes17-18951

W Creswell, J. (2014). Research-Design_Qualitative-Quantitative-and-Mixed-Methods-Approaches Forth Edition. In V. Knight (Ed.), Sage Publication (Fourth Edi). Sage Publication Ltd.

Wang, C. C., Chien, C. H., & Trappey, A. J. C. (2021). On the application of ARIMA and LSTM to predict order demand based on short lead time and on-time delivery requirements. Processes, 9(7), 1–19. https://doi.org/10.3390/pr9071157

Wiyatno, T. N., & Kurnia, H. (2022). Increasing Overall Equipment Effectiveness in the Computer Numerical Control Lathe Machines Using the Total Productive Maintenance Approach. Jurnal Optimasi Sistem Industri, 15(2), 284–292. https://doi.org/10.31315/opsi.v15i1.7284




DOI: http://dx.doi.org/10.22441/oe.2024.v16.i1.104

Refbacks

  • There are currently no refbacks.


Copyright (c) 2024 Operations Excellence: Journal of Applied Industrial Engineering

Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Journal ISSN:

Portal ISSNPrint ISSN: 2085-4293
Online ISSN: 2654-5799

Tim Editorial Office
Operations Excellence: Journal of Applied Industrial Engineering

Magister Teknik Industri Universitas Mercu Buana
Jl. Raya Meruya Selatan No. 1 Kembangan Jakarta Barat
Email: [[email protected]]
Website: http://publikasi.mercubuana.ac.id/index.php/oe
Journal DOI: 10.22441/oe

The Journal is Indexed and Journal List Title by: