Analysis of Building Permit Processing Delays Using Fishbone Diagram, 5 Why-Why Analysis, and 5W+1H Method

Agus Jerry Suarjana Putra, Dewi Nusraningrum

Abstract


Objectives: The objective of this study is to analyze the impact of implementing structured quality management tools, specifically the Fishbone Diagram, Why-Why Analysis, and 5W + 1H method, on reducing project permit processing delays in the construction industry, with a focus on improving efficiency at the transportation industry.

Methodology: This study uses a qualitative research approach, collecting data through interviews, document analysis, and direct observations within the transportation industry. The Fishbone Diagram, Why-Why Analysis, and 5W + 1H method were systematically applied to identify the root causes of permit processing delays and take strategic steps so that permit delays do not occur again.

Finding: The findings reveal that the application of these structured quality management tools significantly reduces permit processing delays by improving coordination between authorities to obtain approval for additional time, supported by clear progress reports and justifications for the causes of delays.

Conclusion: The study concludes that the integration of the Fishbone Diagram, Why-Why Analysis, and 5W + 1H methods in the permit processing workflow effectively addresses operational inefficiencies. Future research should expand on these findings by applying these methods across different companies and regions to improve the management of Building Construction permits so that the Company avoids losses due to project cost overruns.


Keywords


Building Permit; Quality Management Tools; Fishbone Diagram; Project Management.

Full Text:

PDF

References


Abdel Wahed, M. M., & Ismail, T. S. (2022). An online system for issuing buildings permits in light of e-government in Egypt. HBRC Journal, 18(1). https://doi.org/10.1080/16874048.2021.2019447

Al-Hamrani, A., Kim, D., Kucukvar, M., & Onat, N. C. (2021). Circular economy application for a Green Stadium construction towards sustainable FIFA world cup Qatar 2022TM. Environmental Impact Assessment Review, 87. https://doi.org/10.1016/j.eiar.2020.106543

Amilia, E., Fahmi, M., & Hariyanto, B. (2022). ANALISA PERBANDINGAN WAKTU DAN BIAYA PADA KONTRUKSI FULL PRECAST DAN KONTRUKSI KONVENSIONAL (STUDI KASUS : RUMAH TINGGAL DUA LANTAI JAKARTA TIMUR ). Journal of Sustainable Civil Engineering (JOSCE), 4(01). https://doi.org/10.47080/josce.v4i01.1824

Bag, S., Yadav, G., Dhamija, P., & Kataria, K. K. (2021). Key resources for industry 4.0 adoption and its effect on sustainable production and circular economy: An empirical study. Journal of Cleaner Production, 281, 125233.

Chofreh, A. G., Goni, F. A., Malik, M. N., Khan, H. H., & Klemeš, J. J. (2019). The imperative and research directions of sustainable project management. Journal of Cleaner Production, 238, 117810.

Dharma Putra, I. M. Y., & Nusraningrum, D. (2022). Enterprise Resource Planning Implementation: User Satisfaction on Service Information System Quality. MIX: JURNAL ILMIAH MANAJEMEN, 12(3), 443. https://doi.org/10.22441/jurnal_mix.2022.v12i3.006

Dharmayanti, G. C., Sudarsana, D. K., & Guhyathama, I. B. M. (2022). UPAYA PENANGGULANGAN KETERLAMBATAN PELAKSANAAN PROYEK KONSTRUKSI DI KABUPATEN BADUNG. JURNAL SPEKTRAN, 10(1). https://doi.org/10.24843/spektran.2022.v10.i01.p05

Egwim, C. N., Alaka, H., Toriola-Coker, L. O., Balogun, H., Ajayi, S., & Oseghale, R. (2023). Extraction of underlying factors causing construction projects delay in Nigeria. Journal of Engineering, Design and Technology, 21(5). https://doi.org/10.1108/JEDT-04-2021-0211

Elhusseiny, H. O., Nosair, I., & Ezeldin, A. S. (2021a). Systematic processing framework for analyzing the factors of construction projects’ delays in Egypt. Ain Shams Engineering Journal, 12(2). https://doi.org/10.1016/j.asej.2020.10.016

Elhusseiny, H. O., Nosair, I., & Ezeldin, A. S. (2021b). Systematic processing framework for analyzing the factors of construction projects’ delays in Egypt. Ain Shams Engineering Journal, 12(2). https://doi.org/10.1016/j.asej.2020.10.016

Erni, N., & Wijaya, A. S. (2018). Peningkatan Keselamatan Dan Kesehatan Kerja Mengunakan Metode Fault Tree Analysis Dan 5W1H Pada Pt. Homeware …. Metode.

Fashina, A. A., Omar, M. A., Sheikh, A. A., & Fakunle, F. F. (2021). Exploring the significant factors that influence delays in construction projects in Hargeisa. Heliyon, 7(4). https://doi.org/10.1016/j.heliyon.2021.e06826

Fauth, J., Bloch, T., Noardo, F., Nisbet, N., Kaiser, S. B., Nørkjær Gade, P., & Tekavec, J. (2024). Taxonomy for building permit system - organizing knowledge for building permit digitalization. Advanced Engineering Informatics, 59. https://doi.org/10.1016/j.aei.2023.102312

Gartlehner, G., Schultes, M. T., Titscher, V., Morgan, L. C., Bobashev, G. V., Williams, P., & West, S. L. (2017). User testing of an adaptation of fishbone diagrams to depict results of systematic reviews. In BMC Medical Research Methodology (Vol. 17, Issue 1). https://doi.org/10.1186/s12874-017-0452-z

Guinness, A. M., & Heathcote, J. (2022). The Myth of the Post Project Review. In Climate Emergency – Managing, Building , and Delivering the Sustainable Development Goals. https://doi.org/10.1007/978-3-030-79450-7_26

Hikmah, D., Purwanto, S., Ryani, Parasakti, D., Soelton, M., & Arief, H. (2024). MIX: Jurnal Ilmiah Manajemen Towards the Knowledge Management: Improving The Role of Organizational Citizenship Behavior Through the Job Satisfaction. 14i2.009. https://doi.org/10.22441/jurnal_mix

Imaningsih, E. S., Nawangsari, L. C., Saratian, E. T. P., & Wibowo, M. W. (2022). Green Management. Media Edu Pustaka, Jakarta.

Karyatun, S., Yuliantini, T., Saratian, E. T. P., Paijan, P., Soelton, M., & Riadi, E. (2023). Towards The Best Model Good Corporate Governance And Knowledge Management To Improve Performance Through Job Satisfaction. Jurnal Riset Bisnis Dan Manajemen, 16(2), 236-245.

Keselamatan, P., Kesehatan, D., Erni, N., & Syahputra Wijaya, A. (2017). Kerja Mengunakan Metode Fault Tree Analysis dan 5w1h pada PT. In Homeware International Indonesia Jurnal Inovisi (Vol. 13, Issue 1).

Khotimah, A. K., & Beatrix, M. (2022). Analisis Faktor Keterlambatan Waktu Pelaksanaan Proyek Jalan Nasional di Jawa Timur. Jurnal Teknik Sipil Universitas 17 Agustus 1945 Semarang, Vol. 15(No. 2).

Kumar, V., Pandey, A., & Singh, R. (2023). Project success and critical success factors of construction projects: Project practitioners’ perspectives. Organization, Technology and Management in Construction, 15(1). https://doi.org/10.2478/otmcj-2023-0001

Lalmi, A., Fernandes, G., & Souad, S. B. (2021). A conceptual hybrid project management model for construction projects. Procedia Computer Science, 181. https://doi.org/10.1016/j.procs.2021.01.248

Lestari, F., Oktarina, D., & Fadilasari, D. (2022). EVALUASI FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PELAKSANAAN PROYEK KONSTRUKSI. Jurnal Arsitektur Kolaborasi, 2(1). https://doi.org/10.54325/kolaborasi.v2i1.19

Maarif, M. S. (2022). ANALISA PENJADWALAN PROYEK DENGAN METODE PERT DAN CPM PADA PEMBANGUNAN GEDUNG HOTEL DI SIDOARJO. AGREGAT, 7(1). https://doi.org/10.30651/ag.v7i1.9154

Madiawati, P. N., & Pardede, N. L. K. (2023). The Customer Satisfaction as an Antecedent of Purchase Decision in the Post Pandemic Era. MIX: JURNAL ILMIAH MANAJEMEN, 13(2), 404. https://doi.org/10.22441/jurnal_mix.2023.v13i2.010

Manggarani, C. A., Notylia, L. R., & Patiro, S. P. S. (2021). THE NEGATIVE SIDE OF BRAND ATTACHMENT IN PRODUCING NEGATIVE CONSUMER BEHAVIOR. MIX: JURNAL ILMIAH MANAJEMEN, 11(3), 331. https://doi.org/10.22441/mix.2021.v11i3.003

Moradi, S., Kähkönen, K., & Aaltonen, K. (2020). Project managers’ competencies in collaborative construction projects. Buildings, 10(3). https://doi.org/10.3390/buildings10030050

Noardo, F., Wu, T., Arroyo Ohori, K., Krijnen, T., & Stoter, J. (2022). IFC models for semi-automating common planning checks for building permits. Automation in Construction, 134. https://doi.org/10.1016/j.autcon.2021.104097

Nusraningrum, D. (2021). Manajemen Strategi 4.0: Strategi Menghadapi Disruption Di Era Digital.

Nusraningrum, D., Jaswati, J., & Thamrin, H. (2020). THE QUALITY OF IT PROJECT MANAGEMENT: THE BUSINESS PROCESS AND THE GO PROJECT LEAN APPLICATION. Manajemen Bisnis, 10(1). https://doi.org/10.22219/jmb.v10i1.10808

Nusraningrum, D., & Priyono, J. (2018). ANALYSIS OF COST CONTROL, TIME, AND QUALITY ON CONSTRUCTION PROJECT. In Journal of Management and Business (Vol. 17, Issue 1). www.journalmabis.org

Piyathanavong, V., Huynh, V. N., Karnjana, J., & Olapiriyakul, S. (2024). Role of project management on Sustainable Supply Chain development through Industry 4.0 technologies and Circular Economy during the COVID-19 pandemic: A multiple case study of Thai metals industry. Operations Management Research, 17(1) https://doi.org/10.1007/s12063-022-00283-7

Presiden Republik Indonesia. (2008). Peraturan Menteri Pekerjaan Umum Nomor: 24/PRT/M/ 2008.

Putra Wijaya, H., & Khamim, M. (2022). Analisa Faktor-Faktor Resiko Yang Mempengaruhi Keterlambatan Proyek Pembangunan Perumahan Grand Pesona Pandanwangi Malang. Online Skripsi, Manajemen Rekayasa Konstruksi, 3(2).

Rohmah, S. (2023). Pengendalian Kualitas Produk dengan Menggunakan Metoda FMEA dan Pendekatan 5W+1H untuk Penanggulangannya di CV “X.” https://doi.org/10.32734/ee.v6i1.1878

Rorong, R. S., & Budiarso, N. S. (2021). RETRIBUSI IZIN MENDIRIKAN BANGUNAN DAN PERMASALAHANNYA STUDI PADA DINAS PENANAMAN MODAL DAN PELAYANAN TERPADU SATU PINTU KOTA MANADO. Jurnal Riset Akuntansi Dan Auditing "GOODWILL, 12(2), 305–314.

Saratian, E. T. P., Aysa, I. R., & Sudiana, U. (2024). Sustainable Finance: Nurturing Your Savings and the Planet. Journal of Economic, Bussines and Accounting (COSTING), 7(4), 8757-8762.

Septiaji, P., Simanjuntak, M., & Saptono, I. T. (2020). PENGARUH PERSEPSI BAURAN PEMASARAN, PENJUALAN KENDARAAN, DAN PROGRAM LOYALITAS TERHADAP PEMBELIAN BAN DI PASAR REPLACEMENT. MIX: JURNAL ILMIAH MANAJEMEN, 10(3), 321. https://doi.org/10.22441/mix.2020.v10i3.002

Trout, J. (2023). Fishbone Diagram: Determining Cause and Effect. Reliable Plant.

Wardana, E. K. (2021). Faktor-Faktor yang Mempengaruhi Keterlambatan Pembayaran Proyek Gedung di Kota Bandung. Faktor-Faktor Yang Mempengaruhi Keterlambatan Pembayaran Proyek Gedung Di Kota Bandung, 1–7.

Yunus, A. I., Bachtiar, E., Hasan Ramli, Z., Nurpadli, A. M., . A., & Tari, A. (2022). Studi Keterlambatan Proyek Pembangunan Ruko Business Park Citaland City Losari Makassar. Journal of Applied Civil and Environmental Engineering 2(2). https://doi.org/10.31963/jacee.v2i2.3649




DOI: http://dx.doi.org/10.22441/jurnal_mix.2024.v14i3.011

Refbacks

  • There are currently no refbacks.


MIX: Jurnal Ilmiah Manajemen
Journal URL: http://publikasi.mercubuana.ac.id/index.php/Jurnal_Mix
Journal DOI: 10.22441/jurnal_mix
P-ISSN: 2088-1231
E-ISSN: 2460-5328

Editor's Address:

Magister Management Department, Universitas Mercu Buana.
Tedja Buana Building 4th Floor.
Jl. Menteng Raya No. 29, Jakarta 10340.

The Journal is Indexed and Abstracting by:

 

Web
Analytics Made Easy - StatCounter
View My Stats